4-47-01 Thermal insulation I. Quartal 2005   
3-27-01 Wooden box-type windows I. Quartal 2005   
3-36-01 Screed and sealing works I. Quartal 2005   
3-27-03 New wooden doors I. Quartal 2005   
3-25-01 New terrazzo I. Quartal 2005   
3-22-01 Waterproofing and plumbing works for the main roof II. Quartal 2005   
3-31-01 Metal doors and linings II. Quartal 2006   
3-23-01 Plaster and flagstone works II. Quartal 2005   
3-31-03-00a Courtyard roofs IV. Quartal 2005   
3-24-01 New mosaic III. Quartal 2005   
4-50-01 Lightning protection and earthing systems II. Quartal 2005   
3-16-01 Carpentry roof framing in the Stair Hall III. Quartal 2005   
3-37-01 Dry construction works II. Quartal 2006   
3-31-02 Metal works III. Quartal 2006   
3-28-01 New planking I. Quartal 2006   
3-34-01-00b Painting works I. Quartal 2007   
3-27-04-00a New wooden linings + Built-in furniture I. Quartal 2007   
3-22-04 Flat roof sealing + Pressure distribution records II. Quartal 2006   
3-31-07 Closing systems II. Quartal 2008   
4-58-02 Lighting I. Quartal 2007   
4-67-01 Measurement-control-regulation air-conditioning system II. Quartal 2006   
3-27-04-00c Benches I. Quartal 2008   
3-33-02 Final cleaning II. Quartal 2007   
3-12-07 Shell of colonnades I. Quartal 2007   
4-45-01 Kitchen technology systems IV. Quartal 2006